This takt time calculator sets the pace of a line from customer demand and then balances the work across stations. Enter shift length, breaks, shifts per day and daily demand to get takt time and the hourly rate. List the tasks with their times and predecessors and it assigns them to stations under takt, showing each station's load, idle time, line efficiency and balance delay. Paste several lines to get takt and the minimum stations for each. It runs in your browser.
| Daily demand | Takt time | Units per hour |
|---|---|---|
| 210 | 120 s | 30 |
| 420 | 60 s | 60 |
| 840 | 30 s | 120 |
| 1,260 | 20 s | 180 |
Divide available production time by customer demand. 420 minutes (25,200 s) for 420 units gives a 60-second takt.
No. Takt is the pace demand requires; cycle time is how long a station actually takes. Each station's cycle time must be at or under takt.
Total work content ÷ (number of stations × takt). 125 s of work over 3 stations at 60 s takt is 69%.
Split it, speed it up, or duplicate the station so two run in parallel.
No. Everything runs in your browser.
Takt time = available production time (shift length − breaks, × shifts) ÷ customer demand. The theoretical minimum number of stations is the total work content ÷ takt, rounded up. Tasks are then assigned with the ranked positional weight method: each task's weight is its time plus the time of every task that follows it; at each step the heaviest task whose predecessors are done and that still fits within takt is added to the station. Line efficiency = work content ÷ (stations × takt); balance delay = 1 − efficiency.