Takt Time and Line Balancing Calculator

This takt time calculator sets the pace of a line from customer demand and then balances the work across stations. Enter shift length, breaks, shifts per day and daily demand to get takt time and the hourly rate. List the tasks with their times and predecessors and it assigns them to stations under takt, showing each station's load, idle time, line efficiency and balance delay. Paste several lines to get takt and the minimum stations for each. It runs in your browser.

Takt time for a 420-minute day

Daily demandTakt timeUnits per hour
210120 s30
42060 s60
84030 s120
1,26020 s180

When to use it

  1. Set the takt time for a new assembly line.
  2. Work out how many operators a demand change needs.
  3. Rebalance stations after a cycle time change.
  4. Teach lean line balancing with a worked example.
  5. Check whether a task must be split or run in parallel.

How to Use

  1. Enter shift time, breaks, shifts and demand.
  2. Read the takt time.
  3. List tasks as id, seconds and predecessors.
  4. Read the stations, efficiency and idle time.

Features

  1. Takt time and hourly rate
  2. Precedence-aware line balancing
  3. Ranked positional weight method
  4. Efficiency and balance delay
  5. Batch for many lines
  6. 100% client-side

FAQs

How do I calculate takt time?

Divide available production time by customer demand. 420 minutes (25,200 s) for 420 units gives a 60-second takt.

Is takt time the same as cycle time?

No. Takt is the pace demand requires; cycle time is how long a station actually takes. Each station's cycle time must be at or under takt.

What is line efficiency?

Total work content ÷ (number of stations × takt). 125 s of work over 3 stations at 60 s takt is 69%.

What if a task is longer than takt?

Split it, speed it up, or duplicate the station so two run in parallel.

Is anything uploaded?

No. Everything runs in your browser.

Technical Details

Takt time = available production time (shift length − breaks, × shifts) ÷ customer demand. The theoretical minimum number of stations is the total work content ÷ takt, rounded up. Tasks are then assigned with the ranked positional weight method: each task's weight is its time plus the time of every task that follows it; at each step the heaviest task whose predecessors are done and that still fits within takt is added to the station. Line efficiency = work content ÷ (stations × takt); balance delay = 1 − efficiency.

Business & Legal Tools

Business & Legal Tools

  • Process Capability Calculator (Cp, Cpk)
  • Control Chart Builder (X-bar R, I-MR, p)
  • DPMO and Sigma Level Calculator
  • Contract Compare (DOCX and PDF Redline)
  • Legal Deadline Calculator (Court Days)
  • Document Template Filler (DOCX Mail Merge)
  • Sample Size Calculator (A/B Test and Survey)
  • Ad Metrics Calculator (CPM, CPC, CTR, CPA, ROAS)