OEE Calculator

This OEE calculator measures how well a machine or line uses its planned production time. Enter planned time, stop time, the ideal cycle time and the total and good counts, and it gives availability, performance, quality and the overall OEE score, with the minutes lost to each group of the six big losses. Paste a shift log to score every line and shift at once and download the results. It runs in your browser.

420 min planned, 1 s ideal cycle

CaseAvailabilityPerformanceQualityOEE
47 min down, 19,271 made, 18,848 good88.8%86.1%97.8%74.8%
World-class target90%95%99.9%85.4%
No losses100%100%100%100%

When to use it

  1. Score a shift for the daily production meeting.
  2. Compare OEE across lines or plants.
  3. Find whether downtime, speed or scrap is the biggest loss.
  4. Track OEE before and after a SMED or TPM project.
  5. Check a machine vendor's throughput claims.

How to Use

  1. Enter planned time and stop time.
  2. Enter the ideal cycle time.
  3. Enter total and good counts.
  4. Read OEE and the losses, or paste a shift log.

Features

  1. Availability, performance, quality
  2. OEE score with rating
  3. Loss breakdown in minutes
  4. Shift and line batch
  5. CSV export
  6. 100% client-side

FAQs

How is OEE calculated?

OEE = availability × performance × quality. In the classic example, 420 min planned with 47 min down, a 1 s ideal cycle, 19,271 parts made and 18,848 good gives 88.8% × 86.1% × 97.8% = 74.8%.

What is a good OEE score?

85% is widely cited as world class for discrete manufacturing, 60% is typical, and 40% is common where measurement has just started.

What counts as planned production time?

Shift time minus planned stops such as breaks and meetings; unplanned stops and changeovers count as downtime.

Why is my performance over 100%?

The ideal cycle time is set too slow. Use the fastest cycle the machine is designed or proven to run.

Is anything uploaded?

No. Everything runs in your browser.

Technical Details

Availability = run time ÷ planned production time, where run time = planned time − stop time. Performance = ideal cycle time × total count ÷ run time. Quality = good count ÷ total count. OEE = availability × performance × quality, which equals fully productive time (good count × ideal cycle time) ÷ planned production time. Lost time is split into availability, performance and quality losses. Batch mode scores a CSV of lines and shifts.

Business & Legal Tools

Business & Legal Tools

  • Takt Time and Line Balancing Calculator
  • Process Capability Calculator (Cp, Cpk)
  • Control Chart Builder (X-bar R, I-MR, p)
  • DPMO and Sigma Level Calculator
  • Contract Compare (DOCX and PDF Redline)
  • Legal Deadline Calculator (Court Days)
  • Document Template Filler (DOCX Mail Merge)
  • Sample Size Calculator (A/B Test and Survey)