This excavation calculator works out how much soil you're digging out and how many truck loads it makes. Choose a trench, rectangular pit or round pit, enter the dimensions and the side slope, pick the soil type for its swell, and set the truck size. It shows the in-place volume in m³ and cubic yards, the loose volume after bulking and the truck loads. Paste every trench on a site plan to total the job. It runs in your browser.
| Soil | Swell | 1 m³ dug becomes |
|---|---|---|
| Sand / gravel | 12% | 1.12 m³ |
| Common earth / loam | 25% | 1.25 m³ |
| Clay | 35% | 1.35 m³ |
| Blasted rock | 60% | 1.60 m³ |
Length × width × depth for vertical sides; with sloped sides use the average of bottom and top widths.
Soil takes up more space once dug: common earth about 25% more, clay 30–40%, rock 50–60%.
Loose volume ÷ the truck's capacity; a 10 m³ tipper carries about 8 m³ of in-place earth.
Most safety rules require shoring or battering beyond about 1.2–1.5 m deep.
No. Everything runs in your browser.
Trench volume = length × depth × (bottom width + top width) ÷ 2, where top width = bottom + 2 × depth × side slope (horizontal per vertical). Rectangular pits use the prismoidal formula V = d/6 × (A1 + 4Am + A2) and round pits a frustum. In-place (bank) volume is converted to loose volume by the soil's swell (sand about 12%, common earth 25%, clay 35%, blasted rock 60%) and divided by truck capacity for loads. Batch mode reads one trench per row.